25 Years of KNX at the Konzertkirche Neubrandenburg: Modernisation with the PEAKnx Control 12

25 Years of KNX at the Konzertkirche Neubrandenburg: Modernisation with the PEAKnx Control 12

After a quarter of a century in operation, the existing KNX control panel at the Konzertkirche Neubrandenburg failed. In 2026, as the concert hall celebrates its 25th anniversary, Stralsund-based system integrator GePro replaced it with our Control 12 touch panel. The existing visualisation was also replaced with the ELVIS visualisation software from IT GmbH.

Project overview

  • Property: Concert Church
  • Location: Neubrandenburg
  • System integration: GePro
  • Control: KNX-Touchpanel Control 12
  • Visualisation: ELVIS

A concert hall with 25 years of KNX history

The Konzertkirche Neubrandenburg has a remarkable history. Originally St Mary's Church, a building in the North German Brick Gothic style, it was severely damaged during the Second World War and rebuilt between 1998 and 2001 for its new purpose as a concert and event venue, following designs by Finnish architect Pekka Salminen. No longer used for religious services, the former church now houses a modern concert hall within its historic brick structure. Since opening in 2001, it has served as one of the venues of the Neubrandenburg Philharmonic Orchestra and can accommodate more than 800 visitors.

Bild-Collage der Konzertkirche Neubrandenburg

The KNX installation also dates back to the reconstruction and continues to control a significant part of the building's lighting. In addition to the concert hall, the system covers lighting in corridors, exhibition areas and cloakrooms, as well as the building's exterior and tower lighting. The 14 × 12-metre stage is also equipped with stage spotlights controlled via DMX (Digital Multiplex), a control protocol widely used in event technology.

DMX

DMX ("Digital Multiplex") is a fast, digital control protocol from the stage and event technology field, which, in combination with KNX (the worldwide standard for home and building systems technology), is mainly used for dynamic, complex color and lighting effects.

After 25 years, however, the need for modernisation became apparent elsewhere: the existing Proface KNX control panel with an EIB adapter, dating from 1999, had failed in the control room. GePro therefore began looking for a modern replacement that would allow the existing KNX infrastructure to remain in use.

Control 12 touch panel replaces the existing KNX control panel

GePro chose our Control 12 because it can also be used in portrait orientation, meeting a key requirement for the replacement. The challenge was to integrate the new touch panel into the existing mounting arrangement. To achieve this, GePro manufactured a custom frame that allowed the Control 12 to fit into the existing housing. Its black finish also blends in with the dark interior of the control room.

We also offer replacement solutions for older KNX touch panels from various manufacturers. These are designed to accommodate existing mounting arrangements and enable users to upgrade to a modern PEAKnx touch panel. At the Konzertkirche, however, the existing mounting conditions required a custom solution developed by GePro.

ELVIS visualisation on the Control 12

Along with the touch panel, the previous GP-Pro visualisation from Proface was also replaced. Our Control 12 now runs the ELVIS visualisation software from IT GmbH, offering a wide range of control options. One of the main reasons for choosing ELVIS was the flexibility to customise the user interface. The lighting controls needed to have a specific design and offer a similar operating experience to the previous panel. As another Proface display is still in use at the Konzertkirche, the new user interface also needed to harmonise with it.

This is possible because the Control 12 is Windows-based and is not limited to our YOUVI visualisation software. Visualisation solutions from other providers can also be installed and used on our panels.

PEAKnx Control 12 mit ELVIS-Visualisierung

Lighting control in the control room

The Control 12 is installed in the control room of the Konzertkirche, where staff use it to manage the lighting during events. The ELVIS visualisation gives users access to the building's KNX-controlled lighting systems.

As the control room is largely darkened during concerts, the display must not cause glare during operation. The brightness of the Control 12 can be adjusted to suit the lighting conditions, ensuring that the display does not interfere with work in the control room.

Keeping the existing KNX technology in use

GePro provides ongoing support for the Konzertkirche's building technology and continues to maintain the installation following the control panel replacement. With the company based approximately 100 kilometres away in Stralsund, some of the work is carried out remotely. When necessary, its specialists also visit the site in Neubrandenburg.

Long-term support for existing installations is part of GePro's everyday business. The company has been operating for around 30 years and, according to Managing Director Dirk Müller, has supported some projects for almost as long.

Even 25 years after the Konzertkirche opened, the KNX installation dating from its reconstruction remains in operation. Replacing the defective control panel demonstrates how an existing KNX system can be upgraded in a targeted way without having to replace the entire infrastructure.

More about the Control 12